Worker Distribution Dilemma

Start Timer

0:00:00

Upvote
0
Downvote
Save question
Mark as completed
View comments

Let’s say we’re managing a production line for assembling electric scooters, with 10 stations where each has a different average processing time per unit (for example, Station 1 takes 5 minutes, Station 2 takes 3 minutes, and so on).

How would you determine the right metric to use for balancing worker allocation across the stations, and how would you use it to figure out how many workers each station needs?

.
.
.
.
.